Tuesday, 3 March 2015

South Africa: Another Round Of Load Shedding Begins Today, Is Your Area On Today's Schedule? Get In Here And Find Out

img-1

We’re looking at load shedding from Tuesday through Thursday due to a “shortage of capacity to meet the demand”.
According to Eskom:


"The system is extremely constrained today and for the rest of the week. Any extra load or faults in the system may necessitate the need to go into load shedding.

The good news is that Medupi started giving us power as of yesterday. In the midst of many problems and massive delays, it is nothing short of a miracle that part of it is actually working. The coal-fired power station “will pump 794MW into the national grid when it gets up to full power in three months time”, with a total of 4 764MW once all six units are finished in 2017.

You can use this easy to understand load shedding schedule from News24  GridWatch – you can even save applicable areas."

Did you find this information helpful? I would be glad if you let me know in the comment section. Have a great day people!


[Source: News24]